Home / Questions / How long does it take to build a business website?

How long does it take to build a business website?

It usually takes two to six weeks to build a business website of 5 to 15 pages once content is ready. A simple 5-page WordPress site can launch in about two to three weeks. Content delays, extra revisions and custom features are the most common reasons projects take longer.

Owners want a clear answer on how long it takes to build a business website, usually because a launch, campaign or opening date depends on it. The build itself is often quicker than expected. What stretches timelines is waiting for content, feedback and decisions.

build a business website

Here are realistic timelines and how to keep your project on track.

Typical timelines to build a business website

Site typeTypical timeline
One-page or landing page1 to 2 weeks
5-page WordPress site2 to 3 weeks
10 to 15 page site with blog4 to 6 weeks
Site with booking, integrations or custom features6 weeks or more

These assume content is ready and feedback is quick. They are estimates, not promises.

Ready to act on this?

Get a written review of your site, or send us your question and we will reply within 24 hours.

Where the time goes

  1. Planning: pages, features and structure (a few days).
  2. Design: homepage and key layouts, plus revisions (about a week).
  3. Build: pages, forms and responsive layouts (one to three weeks).
  4. Content: adding text and images (depends on readiness).
  5. Testing: phones, browsers, forms and speed (a few days).
  6. Launch: domain, SSL, tracking and final checks (one day).

Read the website development process for detail on each step.

What slows projects down

  • Content arriving late or in pieces.
  • Many people giving feedback separately.
  • New features added mid-project.
  • Waiting for logins, logos or approvals.

How to build a business website faster

  • Write a short brief before you start.
  • Prepare text and photos before design begins.
  • Choose one person to collect and send feedback.
  • Launch core pages first and add extras in a second phase.

Example: a five-page site in three weeks

A dental practice wanted its new site live before a local advertising campaign. It sent a brief, logo, photos and text for five pages on day one. Design was approved in the first week, the build finished in the second, and testing and launch took the third. Another practice with the same scope took ten weeks, because content arrived slowly and several partners sent conflicting feedback. Same work, very different timelines. When you build a business website, preparation decides the date more than development speed does.

Do not skip testing to save time

Rushing launch often means broken forms or slow mobile pages. Google’s Core Web Vitals are worth checking before launch, along with forms and phone layouts. A few days of testing protect every enquiry that follows.

Planning around a launch date

If you need to build a business website for a fixed date, such as an opening or an advertising campaign, share that date in your brief. Your developer can plan backwards: when design must be approved, when content is needed and when testing starts. Leave a small buffer of a week for unexpected delays. Projects with a clear date and a shared schedule launch on time far more often than those with a vague “as soon as possible”. When you build a business website this way, everyone knows what is due and when.

Frequently asked questions

Can you build a business website in one week?

A simple one-page site, yes. Multi-page sites usually need more time for design and testing.

What is the biggest cause of delays?

Content. Sites wait for text and photos more than for development.

Does custom design take longer?

Yes, usually a week or two more than a template-based design.

Can I update the site myself after launch?

Yes. We train you at handover so you can edit content.

Does a blog add time?

Setting up the blog section adds little time. Writing the first articles takes longer, so many owners add posts after launch.

What if I need changes after launch?

Small edits are quick. Bigger changes, such as new sections or features, are planned as a second phase.

Not sure where your site stands?

Send us the details and we will reply within 24 hours with a clear next step.